Dutton Bay Tramway - Progress

Progress - From an Empty Shed to a Model Railway

1998-1999-2000

31 December 00
  • As the year drew to a close, the wipers have been provided for all switchmaster machines, and frog wiring and turnout machine control wiring is in place
  • The PCB for the route control system was built, and during testing a fundamental design flaw found. Unfortunately too late to purchase the extra componentry needed. Work will resume when the shops open...

    27 December 00

  • Yesterday was spent building the power supply for the Staging Yard route control system, based on that in Model Railroader for November 2000.
  • Today saw time spent on designing the actual turnout operation, positioning the ICs on the PCB, and determining the requirement for diodes
  • This evening work began on installing the phosphor-bronze wipers to provide power to the frogs. See photos here and here. These are not my idea, being seen by me first on Laurie Green's layouts.

    23 December 00

  • The basic traction wiring has been completed, thanks to my son spending three hours with a soldering iron. Now I need to wire in the frogs and and the switchmasters. There are pictures here

    22 December 00

  • All the droppers have now been soldered to the rail, and the bus wiring has been run underneath, although not soldered into place yet.
  • All the components for my thumbwheel operation of the Tumby Bay staging yard. Now onto soldering ICs onto PCBs

    18 December 00

  • Over the weekend eight switchmaster machines were installed under the staging yard.
  • A "top coat" of the sky blue was applied over the backdrop over the "window wall". Just the top 30% or so. Looks better now
  • Work also began on installing droppers, or track feeds. Currently there are about 30 or 40 small wires dangling...

    13 December 00

  • The backdrop is now complete - hooray. A study of the painting though shows that there are some places where the coverage is very thin, so a second coat will be needed. Boo!

    4 December 00

  • More backdrop painting. I am now "around the corner" onto the "window wall" - that leaves about 15 feet to go.

    3 December 00

  • Tracklaying on the Staging Yard is well progressed now. All track at the Tumby Bay end is laid, leaving only the Kalanda end and the connecting track to be completed. Photographs are on the Backdrop and Staging Yard page.
  • A coat of brown paint has softened the colour of the framing where the backdrop curves around at the staging yard.
  • The backdrop "sky-ing" has extended so that slightly more than half has been completed. See photographs on the Backdrop and Staging Yard page page.

    30 November 00

  • The backdrop on one of the three walls has been painted - a graduated blue. Pictures are here and here although there isn't much to see.

    29 November 00

  • Layout time has been split between some preliminary work prior to track laying, early days in the building of a small "grain agents shed" which will go on the Anunaka wharf, and painting a test length of the backdrop.
  • Planning continued on a possible alternative track plan, which would allow existing benchwork to be used but return the various stations to their correct orientation accodring to the DBT map.
  • Work also has taken place on the DBT's sister web site, the new Australian Narrow Gauge Web Exhibition.

    26 November 00

  • After spending a weekend with fellow narrow-gauger Stephen Colclough in Queensland, trackwork continued. All of the wooden sleepers are now glued into place at the Tumby Bay end of the staging yard, and the rail on the turnouts has been filed to fit the Peco rail joiners.

    22 November 00

  • The first actual, visible and permanent signs of track laying occurred. About 20 wooden sleepers were glued to the cork to fill the gaps between the PCB sleepers.
  • After evaluating numerous colour cards, a colour was chosen for the sky

    21 November 00

  • Replaced all the fluoro tubes in the shed with 5000 degree "cool daylight" ones.
  • Added another pair of sleepers beyond the frog of a turnout and cut an isolating gap. This is because I think I will need to solder the Peco flextrack to the turnout due to the proximity of the curves.

    20 November 00

  • The weekend saw the cork underlay completed on the staging yard. A photo showing work in progress is here. Whilst the board was out the opportunity was taken to test fit the turnouts, as can be seen here.
  • The PCB ties or sleepers on the turnouts were painted. Firstly with zinc chromate primer, and then with floquil roof brown.
  • Monday night saw the first rail joined - one turnout joined to a length of Peco 009 flex track which has been selected for the staging yard
  • A further Monday activity was cutting lots of turnout or point timbers to length ready for gluing down to the cork.

    17 November 00

  • The turnouts have at last had their last joint soldered. Great stuff. Now I can move into finishing the cork underlay in the staging yard and painting the turnouts. A photo of my last pair of turnouts can be seen here

    16 November 00

  • More evaluation was done of lighting for the permanent layout. A daylight fluoro tube was added to the comparison, as was the exhibition spot lighting. Check out the lighting page

    15 November 00

  • The final turnout is now complete. Those previously constructed will have an extra tie added near "the gap" in an effort to ensure the soldered joint doesn't fail, and this work has begun.

    12 November 00

  • The final turnout is now almost complete, requiring just one tie-bar and some additional sleepers.

    11 November 00

  • A temporary lighting valance was erected to allow comparison of the different fluorescent lights.
  • More work on the cork underlay for the staging yard sees everything done except for the two curved tracks.

    9 November 00

  • After an extended weekend, doing some research at Port Lincoln, I returned to action. The final turnout has begun final assembly, but the new soldering iron tip I installed isn't too good, so it shall be replaced when everything cools down.
  • The new digital camera was put to use, with a couple of photos taken of the backdrop and staging yard.

    29 October 00

  • It seemed like a productive weekend, until I wrote this diary. A busy weekend comes down to a single sentence. The MDF was attached to the Staging Yard framing - after installing risers of course - and then the majority of the cork underlay was glued in place. That's all. Kept me occupied for quite some time...

    26 October 00

  • Spent this evening cutting the PCB sleepers to length and gapping them for isolation. There are lots of sleepers in a pair of turnouts with additional rail at two ends!

    23 October 00

  • Back to work on the turnouts. The last stock rail was filed, and all the rail curved to shape. Soldering comes next...

    22 October 00

  • A weekend spent working on the staging yard baseboard and framing. The MDF was "cookie cut" to accomodate the two levels and two connecting tracks on a grade. The framing for the section was also painted. I am not certain whether this is a severe case of paranoia, but having seen the results of water damage on the exhibition modules not once but three times, I am wary. Especially given that the staging yard is located adjacent to the entry door, with no protection against rain when the door is opened for access.
  • I also have a view that too many layouts look "unfinished", and so I have elected to provide a neat appearance, even with the layout under construction. Consequently the framing was not just sealed against possible water ingress, but the visible sections have been painted with the deep brown used for the fascia. Of course, ultimately none of the framing will be visible, as a fascia will be provided for the whole layout.

    20 October 00

  • I have long ago decided that spending a small amout of time working on the model each day is a "good thing" rather than waiting for the odd day when much time can be devoted to model railway activities. I have taken this a little far recently, with two evenings work producing nothing more than three of the four stock rails filed for the point blades. Still, every little bit helps.

    18 October 00

  • Big News! A digital camera is on the way. In a week or so there will be photos to illustrate the construction progress as it happens, rather than waiting for a film to be finished and processed.

    17 October 00

  • The final undercoat was applied to the backboards. Soon, after some time to work out the best shade of "blue", it will change from a backboard to a skyboard.

    15 October 00

  • A productive weekend saw an additional "half-board" of backboard installed, making about 44 linear feet.
  • Backboard was given two undercoats and now looks pretty and white.
  • The two turnouts under construction had their frog (crossing vee) assemblies soldered together, and the taper on the point blades filed.

    9 October 00

  • Rail was bent and filing began for the last two turnouts
  • The backdrop had screw holes and joints filled.

    7 October 00

  • Work continued in the shed. The last (for now) sheet of masonite was installed. The joists were adjusted under the Staging Yard for the switchmasters. The MDF was given another coat of estapol for sealing.

    4 October 00

  • Two new locomotives were delivered. A pair of EM Baldwins, they run on Lifelike SW-1200 mechanisms. They have been despatched to Peter Knife's house for painting (he does a better job than me!)
  • Back to work. The MDF for the Staging Yard was marked out to ensure the Switchmasters all fitted. Only two joists need moving!
  • Work began on the last pair of turnouts, with all the rail cut to length.

    14 September 00

  • Fourth board screwed and glued into place. Just one to go, but that will need to wait until I return from a short holiday.

    12 September 00

  • After a couple of hours work over two nights, the fourth board has now been "sprung" into position. Not yet permanently mounted - that will occur in a day or two

    9 September 00

  • More work on the backdrop. There are now three sheets permanently attached.

    7 September 00

  • The overlapping pair of turnouts completed. Just one more pair of these overlapping turnouts to go and tracklaying could commence.

    6 September 00

  • Work continued on the pair of turnouts, and they have been attached to about half of the PCB ties expected to be used. Looking good....

    4 September 00

  • The frogs for the two turnouts under construction were assembled, and work began on cutting the PCB ties to the various lengths needed for the overlapping turnout.

    3 September 00

  • The second sheet of backdrop was wet some more, and then repositioned with the correct radius. It is currently just sitting there getting used to the shape - will be screwed into place in a few days.

    2 September 00

  • The first sheet of the backdrop was permanently installed today. Battens for the next sheet were attached to the walls, and after wetting, the second sheet was partially installed. It is currently at about 9" radius - more wetting and gentle "force" should see the board at the required 6" radius ready to be permanently attached.
  • Rail was bent and filed for the next pair of turnouts.

    28 August 00

  • The masonite was sprayed (first time) with water - time will tell how effective the treatment will be at helping the material retain the curve
  • Rail was cut for the first of the overlapping pair of turnouts.

    26 August 00

  • Work moved to the layout room for the first time a while. Some quite substantial support framing was built for the aisle end of the backdrop, and the first sheet of 3mm (1/8") masonite forced into the curve and clamped (with about 20 clamps!) The masonite will be sprayed with water over the next few days, unclamped, and providing everything remains in the proper curved shape, will be permanently attached to the battens.

    25 August 00

  • Six turnouts are now ready to install. Four more to be made - in two overlapping pairs.

    22 August 00

  • Some mass-production of tie-bars began. Six 7mm long strips of thin brass were cut, and six PCB ties cut to length to act as tie-bars. That's all for tonight - soldering and assembly tomorrow.

    21 August 00

  • The first "Steve Hatch" tie-bar was completed and attached to a turnout. It took me three attempts, but it works beautifully.

    19 August 00

  • Another two turnouts completed. The first rail was cut at 2:30 PM, and the turnouts were finished (waiting the tie-bar) by 9:30PM. With breaks for dinner and some odd jobs, I would estimate 5-5.5 hours for them. It does get faster as you go!

    17 August 00

  • Some of the window openings cut for the station building.

    11 August 00

  • The framing for the "removable girders" for the Saltpan module was completed

    10 August 00

  • Work begins on construction of the Warunda station building. To be made from styrene, all the wall panels have been cut out, and the posts cut to length

    7 August 00

  • The two turnouts under construction were taken to the same point of near completion as the others - PCB ties attached, waiting on a tie bar and final adjustment.

    6 August 00

  • Work on the small passenger shed for Wepowie resumed, as a change from constructing turnouts. The shed was primed ready for painting, and the corrugated iron roof added.
  • The turnouts were not totally forgotten though. The curved rails were bent to shape, and a bunch of PCB ties cut to length.

    3 August 00

  • The next two turnouts - these targetted at track 1 and the "kickback" - are well under way. Frogs assembled and all that remains, apart from cleaning up some excess solder - is attachment to the PCB ties

    30 July 00

  • Work continued during the week on turnouts. What was described below as "turnout number 4" was more properly "frog number 4", and although the turnout looks great assembled, I decided that what was needed was a better technique, to increase the percentage of acceptable frogs. A jig, made of timber and aluminium strip after a design by Master Modeller Laurie Green, has made frog assembly much easier and the fifth frog was made into the third turnout in suprisingly little time

    24 July 00

  • The next set of "removable girders" were fabricated, for the Saltpan module. Legs and bearers also cut to length ready for assembly.
  • The frog and point blades were cut, bent and files to shape for turnout number four. Now all we need is to put them together properly!!

    23 July 00

  • Business travel has kept work to a minimum. During the week though there was some progress:
  • Work began on the second turnout, but difficulties with the frog assembly are likely to result in an alternative technique being developed.
  • The final arrangement for Warunda was settled on. This plan adds a few inches to the distance from Kelvin, and moves the overhead crane sidings to the opposite side of the track.
  • More planning ... a proposal to increase the distance between stations, effectively by reversing the orientation of Port Dutton (Anunaka) and the jetty was discussed, and ultimately rejected.
  • Plans for the Warunda station building were studied, with a view to beginning construction soon(ish). It will be a standard SAR plan, slightly smaller than that shown here, built (and photographed) by Peter Knife for his Minnipa layout.

    17 July 00

  • The first turnout was completed tonight, as well as some planning for the Warunda dual-gauge interchange

    16 July 00

  • Family activities kept me away from the railway for much of the day. I did manage to draw the Fiddle/Staging yard plan on the MDF, and also adjusted the "notches" on the Kelvin modules. Preliminary work on the legs for the Saltpan girders was also completed

    15 July 00

  • Some "non-essential" tasks performed. Some more of the shed walls were sealed, and the fascia side of the existing Kelvin modules were painted brown. At an exhibition this is the inside, and its appearance not so important. I got sick of walking into the room and being confronted by white plaster and bare timber.
  • Research undertaken for the new station buildings needed at Warunda and Port Dutton.

    13 July 00

  • Almost completed my first turnout tonight. You can see the results here. My "pride and joy" is in the middle, while a Railway Engineering #6 sits on the right. On the left is a Bemo HOe turnout, which is very close to a #5, and which my turnouts will hopefully replace on Anunaka. There is still a little work to do - the gaps need cutting in the point rails, and a tiebar needs to be added. I shall learn from this - subsequent turnouts will have the ties perpendicular to the straight stock rail, and better spaced. I must admit that I had not made a drawing of the tie spacing, so they were done by eye.

    10 July 00

  • My first attempt at a turnout didn't work too well, but the second one is looking much better. Building a jig to hold the rails in place before attaching the masking tape certainly seems to help greatly. Still a long way to go though before I can say "I built a turnout..."

    8 July 00

  • Notches completed in the Kelvin boards, so they can now be positioned correctly on the framing
  • The bottom batten for the backdrop installed over most of the layout. Not only will this piece of 2x1 have the lower edge of the backdrop attached, but also provides a firm locator for the exhibition modules.
  • A couple of sheets of blue paper have been temporarily attached to give me an idea of suitable backdrop heights. Currently I am considering either cutting a metre width of PVC roofing material in half, or cutting 2400x1200 sheets of styrene in half, giving either 500mm or 600mm height. The two sheets are at these two heights, and will give me a chance to review my preferences over the next few days.
  • Began work on my first scratch built turnout, using the tutorial produced by Steve Hatch of Railway Engineering, suitably modified for Number 5 turnouts in HOn30. (Email me for a drawing to match the Bemo #5 turnouts) Rail has been cut, bent, and filed where necessary. Soldering will begin next time...

    7 July 00

  • The Kelvin "butt piece" was reattached, this time in the correct place.
  • Work on cutting notches in the (current) fascia side has begun, with the first one completed - needing two boards to be cut since the upward extension of one of the legs coincided exactly with a module join. Bummer, eh!

    6 July 00

  • Kelvin was assembled on the benchwork tonight, positioned correctly, and some additional timber screwed in place to provide a solid anchor for Kelvin. Unfortunately it was discovered afterwards we had made a slight mistake, and will need to do it all again. That's life, I guess. It does look good though, seeing Kelvin at a resonable track height of 51 inches, and gives me a great idea of what height backdrop I will be needing.
  • Planning and equipment gathering is underway for my major project, building the turnouts for the fiddle/staging yard. Expect an announcement on the weekend.

    2 July 00

  • A quiet weekend, railway-wise. Spent some time on the web site update, and ran a roll of film through the camera (look for some images of construction soon). Sealed the other side of the MDF

    30 June 00

  • The MDF for the fiddle yard was cut to size, and given a sealing coat of paint on one side.
  • Some time was spent on the design of the fiddle yard to try and maximize the amount of space while retaining #5 turnouts as a minimum.

    29 June 00

  • Another two days has seen the Warunda section of the benchwork completed, with "removable" girders installed although the joists will wait for more accurate position of turnouts.
  • Some "mini-girders" have been installed to help support Kelvin, which will have six inches (150mm) of permanent scenery behind it.
  • The 9mm MDF sheet for the Fiddle Yard has been marked out ready for cutting.
  • Another pair of removable girders have been made, waiting for assembly and later installation. These are for the Saltpan area.

    27 June 00

  • The "Fiddle Yard" benchwork has been completed. The "removable" girders are in place, and joists ready for the flat-top MDF sheet have been installed

    24 June 00

  • Continuing work on the benchwork. The permanent L-girders have been erected now. Next is a start on the "removable" L-girders and framing

    19 June 00

  • The second permanent pair of L-girders were installed, on the end wall

    18 June 00

  • At last, something which takes up room space - The first pair of "permanent" L-girders were installed, on the long window wall, to support Kelvin

    17 June 00

  • Today, with the help of my son and his mate, (not to mention the new mitre saw) we assembled eight L-girders of various lengths

    11 June 00

  • The purchase of a compound mitre saw and some timber meant that there was nothing stopping me beginning work. Not much mind, but the end of the evening saw eight legs screwed firmly to the wall. Now for the L-girders..

    April 00

  • Hobsons Bay, the Easter exhibition. On our return we carried the modules into the shed and shut the door ... time for a rest

    31 March 00

  • First test of the sequence planned for Hobsons Bay

    26 March 00

  • The new road was completed, with ground cover added around the area to remove some of the flat, brown appearance.
  • Decoder installed in the Lilliput.

    21 March 00

  • Road to the wharf "dug out" to be scenicked in genuine Eyre Peninsula dirt.

    18 March 00

  • Decoders installed in the two remaining Bemos

    29 February 00

  • All wiring for new panel completed, and control of Anunaka is now by a new "start-of-the-art" unit. Well, a new unit, anyway

    27 February 00

  • In a new world record, the replacement control panel for Anunaka is completed in just one day's work. Properly anchored sockets are also installed under the two Anunaka boards.

    26 February 00

  • Wiring woes! A dead spot is found, and during work to track it down one of the switch machine stops operating. Eventually a couple of broken pins on the old Centronics connector used to hook up the old Anunaka control panel to the layout. As these were fixed another wire dropped off. I think that removal of all the block wires has meant cable loom is less secure now, so that any weak links will eventually break. Decision taken to construct a new panel, matching that at Kelvin.
  • A small storage shed is installed in the loco fuelling area at Anunaka

    20 February 00

  • First train runs on whole layout under DCC control.

    12 February 00

  • Both Anunaka modules converted to DCC bus wiring. All modules now are DCC-ready, waiting to be reassembled and hooked up

    11 February 00

  • Saltpan module done - Wharf board "up on the bench" waiting to be attended to.

    10 February 00

  • All Kelvin modules rewired to the busses. Locomotives run between Fiddle Yard and Kelvin using the EasyDCC system unit, all I have until the hand controllers are purchased in April.

    5 February 00

  • Final conversion of the wiring to allow DCC operation begins. The existing track feeds are cut, and the wires connected to the previously installed "bus" wires. The Fiddle Yard module was done tonight.

    1 February 00

  • The newest loco, EIMCO #66 is fitted with a decoder

    30 January 00

  • RM97 has its decoder fitted

    26 January 00

  • Decoder installed into #52, the Jackrabbit, and another in the second Bemo

    17 January 00

  • Decoder installed into #65, the 830 class

    15 January 00

  • The first Bemo has its frame sliced to allow for a DZ121 decoder. Nerve wracking, an expensive locomotive to be attacking with a hacksaw and Dremel.

    3 January 00

  • The conversion the DCC begins, with a decoder added to RM96. Ground cover added beneath the newly installed water tank

    30 November 99

  • Minnipa water tower installed in the Anunaka wye. Sundry electrical gremlins affecting operation tracked down and corrected.

    27 November 99

  • The DBT is erected in its exhibition configuration. For the first time since the Liverpool exhibition more than a year ago, trains have run on the Dutton Bay. At this stage, still under analog control.

    21 November 99

  • The last two modules, Anunaka and Wharf board, have their bus wires and sockets added to facilitate DCC operation

    19 November 99

  • The Saltpan module had "bus" wiring installed

    16 November 99

  • The fourth and last Kelvin board "bussed"

    13 November 99

  • The next two Kelvin boards "bussed"

    11 November 99

  • The first of the four Kelvin boards "bussed" for DCC

    9 November 99

  • Preparation for adding the Minnipa water tower to Anunaka

    7 November 99

  • The Fiddle Yard and Corner Board wiring had preliminary work done to the wiring in preparation for DCC> This entails adding "bus" wires and sockets for attaching to neighboruing modules, although at this stage the block wires to individual track sections are not being removed.

    1 October 99

  • The "sparkie" hooked everything up. Flick a switch and twelve fluoro tubes burst into life. While the light is not as bright as using daylight rated tubes, it is certainly bright enough for a model railway room, and the light temperature matches the incandescent flood lights used to build and exhibit the layout. The shed is now officially a railway room

    30 September 99

  • Light fittings installed. Electrician arrives on Friday.

    28 September 99

  • In anticipation of the electrician arriving, I purchased six double tube fluorescent light fittings, and order 12 2700 degrees "incandescent" tubes.

    27 September 99

  • I celebrate my birthday by finishing the ceiling. With all walls and the ceiling panelled the shed is starting to look like a room. Now for the electrician to complete wiring everything up.

    26 September 99

  • The ceiling panelling (and insulation) moves towards "almost" completion, with much valuable assistance from son Chris and wife Lin.

    15 August 99

  • Panelling of the shed ceiling begins in a small way - some white panels cut to length, although nothing attached to the top spans yet.

    8 August 99

  • The Wepowie passenger shed has all walls finished. Waiting internal painting before adding the roof.

    11 July 99

  • Panelling of the shed walls is finally completed. Almost six weeks after it began!

    7 July 99

  • Some "real" modelling - construction starts of a small 6'x6' passenger shelter to be located at Wepowie.

    4 July 99

  • Panelling on the last wall, the short one with the doorway, begins.

    27 June 99

  • More panelling - the long wall completed and the end wall done.

    30 May 99

  • Panelling progresses. Half of the long left-hand wall completed.

    23 May 99

  • The shed begins to be finished, with wall panels installed on the long, right-hand wall.

    18 April 99

  • Insulation basically completed - only the peaks on the end walls left to do. Wall panelling purchased

    6 March 99

  • More insulation - the end wall

    22 February 99

  • The first insulation installed. Fibreglass "batts" taped into place along the long, right hand wall

    25 January 99

  • The "rough-in" electrical work was done - cabling was brought into the building and to the various powerpoints and light fitting locations

    3 January 99

  • Two coats of grey paving paint applied to the floor

    31 December 98

  • The concrete floor is given an acid bath to prepare for painting

    28 December 98

  • Enthusiasm regained, work finally begins on the conversion of the shed to a railway room. 44 wooden studs are installed at strategic locations around the walls to facilitate panelling

    October 98

  • With some portable floodlights hanging from the rafters, the shed provided a weatherproof location to complete the detailing of Kelvin prior to the Liverpool exhibition
  • After towing the trailer 900km from Sydney to Mitcham in the rain, we drop the modules on the floor, shut the door, and forget about model railways for a while

    19 September 98

  • The shed is built, by a team of three or four, in two days. 5x6 metres it looks "huge" - empty and bare

    20 January 98

  • Before the shed ... the five 100' (30 metre) high cypress trees which adorned our back yard were removed. It took eight months before the back yard, previously covered in pine needles, but more recently with wood chips, had recovered enough to allow a concrete slab to be poured.

    Return to the DBT Home Page

    Return to the DBT Progress Page